Mooring winch brakes should be tested at regular intervals, not exceeding _____. Choose the correct period from below?

✓

Direct Answer

Option B: 12 months

Mooring winch brakes require regular testing to ensure their reliability and holding capacity. A maximum interval of 12 months is standard practice to maintain safety standards, ensuring the brakes can effectively secure the vessel and prevent uncontrolled movement, as often stipulated in company SMS.

All Options

A
18 months
B
12 months (Correct Answer)
C
24 months
D
30months

Detailed Explanation & Context

Mooring winch brakes require regular testing to ensure their reliability and holding capacity. A maximum interval of 12 months is standard practice to maintain safety standards, ensuring the brakes can effectively secure the vessel and prevent uncontrolled movement, as often stipulated in company SMS.

Relevant Framework: STCW 2010 Manila Amendments • DG Shipping E-Learning & Exit Exam Standards • Advanced Training for Chemical Tanker Cargo Operations (CHEMCO).

Advertisement

Practice Full CHEMCO Set 9

Test yourself with 30 interactive questions, live timer, and instant score.

Launch Practice Simulator →

Question Discussion & Notes

0

Have a doubt, memory trick, or exam update? Share your insights with fellow mariners.

Leave a Comment / Clarification

By posting, you agree to our Terms & Moderation Policy.

Loading mariner discussions...