Q3 (16 Marks) Boilers & Steam 🔥 Repeated 9x in exams
MEKG • Written Exam

You were asked to join a ship as a second engineer. During briefing, you were informed about frequent exhaust gas economiser uptake fires happening onboard. Prepare a plan to reduce exhaust gas economiser uptake fires. How will you monitor the progress of your plan and what instructions you will issue to the watch-keepers?

Appeared In: Feb 2021Dec 2019Sep 2019Mar 2019Feb 2019Jan 2019Oct 2018Sep 2018Apr 2018

✓ Verified Model Answer (Text Solution)

Structured for DG Shipping MEO Class II examination scoring criteria.

Exam Ready
Plan to Reduce Boiler Uptake Fires:

Preventive Maintenance Schedule

  • Carry out regular cleaning, inspection, and adjustment to ensure optimal air-fuel ratio for complete combustion. This minimises the production of soot and unburnt carbon particles.
  • Ensure the fuel oil fed to the boiler is properly treated to minimise impurities that contribute to incomplete combustion.
  • Conduct frequent inspections to identify and address any issues like burner misalignment, damaged refractory, or excessive soot accumulation before they escalate into a fire.
  • Whenever a flame failure occurs, immediately investigate and rectify the root cause to prevent prolonged incomplete combustion. Do not attempt repeated re-ignition until the cause is identified and resolved.

Soot Removal:
  • Implement a more frequent soot-blowing schedule: Develop a revised soot-blowing schedule that is more frequent than the current practice, balancing the need for soot removal with the risk of accelerating a small fire. The schedule should be based on soot accumulation monitoring, possibly through visual inspection or automated monitoring systems. (This is an important addition because merely avoiding soot blowers during a fire isn't enough – we must remove soot before fires start.)
  • Explore the feasibility of alternative soot removal methods such as water washing (potentially utilizing automated systems), to reduce the reliance on soot blowers.

Emergency Procedures (in case of fire): Fire in boiler uptake takes place in three stages:

(i) Normal Soot Fire:

  • Inform C/E and senior engineer
  • Start standby generator
  • Stop the main engine
  • Continue water circulating pump
  • Do not use soot blowers
  • Ensure exhaust valves are closed and cover turbocharger air filter
  • Start external boundary cooling
  • Use water dosing (for fire fighting) if fitted.

(ii) Hydrogen or Metal Fire:

  • Stop the main engine (if not already stopped)
  • Stop boiler water circulating pump
  • Shut all inlet/outlet valves in water circulating lines
  • Drain water from pipelines
  • Continue boundary cooling
  • If a fixed fire fighting system is fitted, activate it.
  • Monitor uptake temperature
  • After the fire is out, conduct thorough water washing
  • Inspect uptake for damage.


Monitoring and Watch Keeper Instructions:

Watchkeepers will be instructed to continuously monitor the following parameters and report any deviations immediately:

  1. Any significant rise indicates potential fire.
  2. Visible sparks or flames are clear indications of a fire.
  3. Activating high-temperature alarms necessitates immediate investigation.
  4. While not a direct indicator of fire, it may be a symptom of blocked flue gas pathways due to soot.
  5. Visual monitoring during routine inspections, aided by potentially installed soot accumulation sensors.