HV Exit Exam • Set 1 Question 3 of 30

What safety document MUST be issued before performing maintenance on High Voltage switchgear?

✓

Direct Answer

Option C: High Voltage Permit to Work (PTW) and Sanction to Test

A formal High Voltage Permit to Work (PTW) and Sanction to Test are mandatory under international safety management codes. These documents ensure the system is isolated, locked, and verified safe by an authorized person, preventing accidental re-energization while personnel are exposed to hazardous live components during maintenance.

All Options

A
Verbal approval
B
Deck log entry
C
High Voltage Permit to Work (PTW) and Sanction to Test (Correct Answer)
D
Hot Work Permit only

Detailed Explanation & Context

A formal High Voltage Permit to Work (PTW) and Sanction to Test are mandatory under international safety management codes. These documents ensure the system is isolated, locked, and verified safe by an authorized person, preventing accidental re-energization while personnel are exposed to hazardous live components during maintenance.

Relevant Framework: STCW 2010 Manila Amendments • DG Shipping E-Learning & Exit Exam Standards • High Voltage Safety Officer & Switchgear Operations (HV).

Advertisement

Practice Full HV Set 1

Test yourself with 30 interactive questions, live timer, and instant score.

Launch Practice Simulator →

Question Discussion & Notes

0

Have a doubt, memory trick, or exam update? Share your insights with fellow mariners.

Leave a Comment / Clarification

By posting, you agree to our Terms & Moderation Policy.

Loading mariner discussions...