Which would be the appropriate arrangement for entering into a DB tank through the ductkeel?

✓

Direct Answer

Option D: Separate enclosed space entry permit for both spaces including standby person outside both

Entering a duct keel and then a double-bottom tank constitutes entry into two distinct enclosed spaces. Each space requires a separate, valid enclosed space entry permit, as per SOLAS and ISGOTT. A dedicated standby person must be positioned outside each entry point to ensure continuous monitoring and immediate assistance for personnel inside.

All Options

A
Entry permit for ductkeel and standby person at the entrance
B
Entry permit for DB tank and standby person loacated inside ductkeel outside DB tank
C
Combined entry permit for both but standby person ductkeel entrance and DB entrance
D
Separate enclosed space entry permit for both spaces including standby person outside both (Correct Answer)

Detailed Explanation & Context

Entering a duct keel and then a double-bottom tank constitutes entry into two distinct enclosed spaces. Each space requires a separate, valid enclosed space entry permit, as per SOLAS and ISGOTT. A dedicated standby person must be positioned outside each entry point to ensure continuous monitoring and immediate assistance for personnel inside.

Relevant Framework: STCW 2010 Manila Amendments • DG Shipping E-Learning & Exit Exam Standards • Advanced Training for Chemical Tanker Cargo Operations (CHEMCO).

Advertisement

Practice Full CHEMCO Set 11

Test yourself with 30 interactive questions, live timer, and instant score.

Launch Practice Simulator →

Question Discussion & Notes

0

Have a doubt, memory trick, or exam update? Share your insights with fellow mariners.

Leave a Comment / Clarification

By posting, you agree to our Terms & Moderation Policy.

Loading mariner discussions...