Question 20 of 30

The design of the secondary barrier, including spray shield if fitted will be __________

A
it is capable of containing any envisaged leakage of liquefied gas fuel for a period of 15 days
B
physical, mechanical or operational events within the liquefied gas fuel tank
C
failure of a support or an attachment to the hull structure will not lead to loss of liquid tightness of both the primary and secondary barriers
D
All the above
Advertisement

Answer & Explanation

The correct answer is Option D: All the above.

This question is frequently asked in the DG Shipping exit exams for maritime courses. Practicing similar questions in the interactive simulator helps improve recall and exam success.