Deck General USCG Question #4649 (Set 149)

While drilling loaded as shown in Sample Load Form Number 4 (Drilling), the DEEP DRILLER suffers an unexpected but slowly increasing port and forward inclination. The wind and waves are light. This inclination could have been caused by __________.

Official USCG Answer & Rule Citation

Correct Answer: Option A — ballast tanks equalizing into tank 1P

Slowly increasing inclinations in calm conditions typically stem from internal liquid shifts like ballast water equalizing into tank 1P. Free communication and uncontrolled cross-flooding create gradual weight shifts, unlike sudden external force failures.