Deck General USCG Question #5209 (Set 162)

When elevating the COASTAL DRILLER in 100 feet of water, the unit should be placed at an air gap of __________.

Official USCG Answer & Rule Citation

Correct Answer: Option A — 35 feet

Air gap requirements for mobile offshore drilling units are specified in the operating manual to clear crest heights of design storm waves. For the COASTAL DRILLER in 100 feet of water, the required operational air gap is strictly set at 35 feet.

100% Free & Open Access — No daily limits, paywalls, or gated answers on BrightMariner.