Deck General USCG Question #539 (Set 16)

The signal man assisting the crane operator first taps his elbow with one hand and then proceeds to use regular signals. This is the signal to __________.

Official USCG Answer & Rule Citation

Correct Answer: Option D — use the whip line

Standard crane hand signals dictate that tapping the elbow with one hand precedes auxiliary hoist or whip line operations. The subsequent standard motion signal then directs the crane operator regarding the specific movement of that whip line.