Deck General USCG Q#3528 (Set 112)

On a MODU, each emergency generator must be tested at least once each __________.

Official USCG Answer & Rule Citation

Correct Answer: Option B — month

Title 46 CFR regulations mandate that each emergency generator on a MODU must be operationally tested at least once each month to verify reliable starting and load-carrying capability under simulated blackout conditions.