If a drill required by regulations is not completed, the Master or person in charge must __________.

Official USCG Answer & Rule Citation

Correct Answer: Option B — log the reason for not completing the drill

46 CFR regulations require that if a mandated safety drill cannot be completed due to operational constraints, the reason must be formally logged in the official logbook to demonstrate regulatory due diligence.