Marine Electrical Systems USCG Q#1055 (Set 36)

Before working on an electric cargo winch master switch or controller, what should be done?

Official USCG Answer & Rule Citation

Correct Answer: Option B — open the circuit breaker in the power supply and tag-out

Lockout/tagout procedures under OSHA and marine electrical safety guidelines require opening the primary power supply circuit breaker and securing it with tags before servicing controllers to prevent accidental energization and electrical shock.

Advertisement