Engine Refrigeration (Supplementary) USCG Question #41 (Set 1)

After the refrigerant has been recovered, leaks repaired if necessary, the system ideally should undergo a dehydration evacuation prior to recharging with refrigerant. As shown in the illustration, besides the vacuum pump suction manifold isolation valve being opened, what would be the proper valve positions to accomplish and prove the evacuation? GS-RA-51 Illustration GS-RA-51: the U.S. Coast Guard has not released this illustration.

Official USCG Answer & Rule Citation

Correct Answer: Option A — Valves 1, 2, and 3 should be in the mid-position and the low-side gauge manifold hand valve should be closed, and the high-side gauge manifold hand valve should be open.

Achieving a complete system evacuation requires opening system service valves to their mid-position to clear all internal passages while properly routing manifold gauge valves to the vacuum pump.