After the refrigerant has been recovered, leaks repaired if necessary, the system ideally should undergo a dehydration evacuation prior to recharging with refrigerant. As shown in the illustration, besides the vacuum pump suction manifold isolation valve being opened, what would be the proper valve positions to accomplish and prove the evacuation? GS-RA-51 Illustration GS-RA-51: the U.S. Coast Guard has not released this illustration.
Official USCG Answer & Rule Citation
Correct Answer: Option D — Valves 1, 2, and 3 should be in the mid-position and the low-side gauge manifold hand valve should be closed, and the high-side gauge manifold hand valve should be open.
Deep dehydration evacuation requires isolating the vacuum pump while utilizing manifold and system service valves in mid-position to evacuate all sectors simultaneously, ensuring both high and low sides achieve the required micron level for moisture removal.