GASCO Exit Exam • Set 8 Question 12 of 30
What should be the vessel's trim and list during gauging for custody transfer?
✓
Direct Answer
Option D: Upright and even keel
The correct answer is Upright and even keel. This complies with established gas tanker operational standards, thermodynamics, and the IGC Code safety requirements.
All Options
A
Upright and 1 m down by stern
B
Upright and 0.5 m down by stern
C
There are no restrictions trim and list
D
Upright and even keel
(Correct Answer)
Detailed Explanation & Context
The correct answer is Upright and even keel. This complies with established gas tanker operational standards, thermodynamics, and the IGC Code safety requirements.
Relevant Framework: STCW 2010 Manila Amendments • DG Shipping E-Learning & Exit Exam Standards • Advanced Training for Liquefied Gas Tanker Cargo Operations (GASCO).