Type a keyword to start searching...

Use ⌘K or Ctrl+K to search from anywhere
GASCO Exit Exam • Set 12 Question 19 of 30

Onboard an LNG tanker with NO 96 containment system, with minor membrane leakage, which of the following it not a recommended remedial action?

✓

Direct Answer

Option C: Alter ship's course and speed to increase pressuree within damageed insulation spaces

In Gaztransport & Technigaz NO 96 membrane containment systems, Invar membranes and perlite insulation boxes maintain cargo containment and thermal insulation.

All Options

A
Check and log gas concentration and temperature on the damageed insulation spaces frequently
B
Ensure at all times secondary space pressuree>damageed primary pressuree +0.5 to 10 bar
C
Alter ship's course and speed to increase pressuree within damageed insulation spaces (Correct Answer)
D
Check location of crack by using vent cock located on nitrogen supply and exhaust

Detailed Explanation & Context

In Gaztransport & Technigaz NO 96 membrane containment systems, Invar membranes and perlite insulation boxes maintain cargo containment and thermal insulation.

Relevant Framework: STCW 2010 Manila Amendments • DG Shipping E-Learning & Exit Exam Standards • Advanced Training for Liquefied Gas Tanker Cargo Operations (GASCO).

Advertisement

Practice Full GASCO Set 12

Test yourself with 30 interactive questions, live timer, and instant score.

Launch Practice Simulator →

Question Discussion & Notes

0

Have a doubt, memory trick, or exam update? Share your insights with fellow mariners.

Leave a Comment / Clarification

By posting, you agree to our Terms & Moderation Policy.

Loading mariner discussions...