GASCO Exit Exam • Set 12 Question 24 of 30

Onboard an LNG carrier, with NO 96 membrane containment system, what is the indication of failure of the primary membrane and primary insulation space?

✓

Direct Answer

Option A: Temperature drop in secondary space temperature probes

In Gaztransport & Technigaz NO 96 membrane containment systems, Invar membranes and perlite insulation boxes maintain cargo containment and thermal insulation.

All Options

A
Temperature drop in secondary space temperature probes (Correct Answer)
B
Temperature drop in cofferdam space temperature probles
C
Temperature drop in wing ballast tank space temperature probles
D
Temperature drop on main deck temperature probles

Detailed Explanation & Context

In Gaztransport & Technigaz NO 96 membrane containment systems, Invar membranes and perlite insulation boxes maintain cargo containment and thermal insulation.

Relevant Framework: STCW 2010 Manila Amendments • DG Shipping E-Learning & Exit Exam Standards • Advanced Training for Liquefied Gas Tanker Cargo Operations (GASCO).

Advertisement

Practice Full GASCO Set 12

Test yourself with 30 interactive questions, live timer, and instant score.

Launch Practice Simulator →

Question Discussion & Notes

0

Have a doubt, memory trick, or exam update? Share your insights with fellow mariners.

Leave a Comment / Clarification

By posting, you agree to our Terms & Moderation Policy.

Loading mariner discussions...