Type a keyword to start searching...

Use ⌘K or Ctrl+K to search from anywhere
CHEMCO Exit Exam • Set 6 Question 5 of 30

When the cofferdam to be purged to check the leakage and remove the leaked oil?

✓

Direct Answer

Option B: Before starting the cargo operation and after the cargo operation is completed

Cofferdams must be purged and tested for leakage both before commencing cargo operations to ensure integrity and after completion to verify that no cargo has leaked into them during the transfer, as per safe operational procedures.

All Options

A
Before starting the cargo operation
B
Before starting the cargo operation and after the cargo operation is completed (Correct Answer)
C
During the cargo operation
D
After the cargo operation is completed

Detailed Explanation & Context

Cofferdams must be purged and tested for leakage both before commencing cargo operations to ensure integrity and after completion to verify that no cargo has leaked into them during the transfer, as per safe operational procedures.

Relevant Framework: STCW 2010 Manila Amendments • DG Shipping E-Learning & Exit Exam Standards • Advanced Training for Chemical Tanker Cargo Operations (CHEMCO).

Advertisement

Practice Full CHEMCO Set 6

Test yourself with 30 interactive questions, live timer, and instant score.

Launch Practice Simulator →

Question Discussion & Notes

0

Have a doubt, memory trick, or exam update? Share your insights with fellow mariners.

Leave a Comment / Clarification

By posting, you agree to our Terms & Moderation Policy.

Loading mariner discussions...